Interstate 465 construction begins next week on the northeast side

construction_2.jpg
Posted at 7:00 PM, May 20, 2019
and last updated 2019-05-21 00:25:40-04

INDIANAPOLIS — Construction season will get underway next week on I-465 on the northeast side.

According to a release from the Indiana Department of Transportation, workers will patch and repave segments of I-465 and I-69 from U.S. 31 down to I-70.

Work is scheduled to begin after Memorial Day and continue through October. The project will be completed in four segments with at least one lane open in each direction.

Here's a look at what to expect and when.

Segment 1: I-465 east and west from White River Bridge to I-69

  • End of May to middle of August
  • Crews will work on the eastbound inside lanes first
  • Work will be completed on nights and weekends
  • 8 p.m. to 6 a.m. the next morning

Segment 2: I-465 east and west from U.S. 31 to White River Bridge

  • Beginning of June to Middle of August
  • Weekend lane closures
  • 8 p.m. to 6 a.m. Monday morning

Segment 3: I-69 N/S from I-465 to S.R. 37

  • Middle of June to End of July
  • Work will be completed on nights and weekends
  • 8 p.m. to 6 a.m. the next morning

Segment 4: I-465 E/W from I-69 to I-70

  • Beginning of August through October
  • Work will be completed on nights and weekends
  • 8 p.m. to 6 a.m. the next morning